Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock From Shasta Street to Wickshire Street Resurfacing Project (Contract No. 23-CG0217/AP; Amount: $66,349.25)
body
BRIEF OVERVIEW
Final Close-Out of Contract with Goodwin Bros. Construction, Inc., for the Ridge Manor Road Paving SCOP 448504-1-54-01 Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock - SFGA project awarded by the Board on April 23, 2024, Doc Id. No. 13766, to Goodwin Bros. Construction, Inc., in the amount of $970,345.09.
Change Order One (1) was requested to add Line 3 with a previous balance of $0.09, which was mistakenly closed out during rollover for new fiscal year and to add $67,348.65. Change Order One (1) was approved by the Chief Procurement Officer (CPO) on November 12, 2024, in the amount of $67,348.74. Purchase order was increased from $970,349.09 to $1,037,693.83.
Change Order Two (2) in the amount of -$314,908.74 to close out the purchase order due to project completion was approved by the CPO on April 14, 2025. The purchase order was decreased from $1,037,693.83 to $722,785.09.
The Final Contract amount is $722,785.09 (PO No. 24000825).
The work has been completed and Goodwin Bros. Construction, Inc., has submitted its Final Pay Application No. Five (5) in the amount of $66,349.25.
FINANCIAL IMPACT
Funding in the amount of $66,349.25 is available in the following accounts:
Expense:
Fund: 1013 - Constitutional Gas Tax, Department: 34602 - DPW- Ridge Manor Road Paving, Account: 5616313 - Improv-Surface Treatment. Amount: $31,800.00
Balance Sheet:
Fund: 1013 - Constitutional Gas Tax, Account: 2050067 - Retainage - Goodwin Construction: Amount: $34,549.25
LEGAL NOTE
The Board has the authority to act on this item pursuant to Part II, Chapter 2, Article V of the Hernando County Code of Ordinances. No notices of lien or claims of lien have been filed on the project.
recommendation
RECOMMENDATION
It is recommended the Board approve Final Pay Request No. Five (5) in the amount of $66,349.25 to Goodwin Bros. Construction, Inc., to close out the Ridge Manor Road Paving SCOP 448504-1-54-01 Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock - SFGA project under Contract No. 23-CG0217/AP.
The final contract amount is $722,785.09, a decrease of $247,560.00 from BOCC award.