File #: 15865   
Type: Agenda Item Status: Adopted
File created: 4/30/2025 In control: Board of County Commissioners
On agenda: 5/27/2025 Final action: 5/27/2025
Enactment date: Enactment #:
Title: Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock From Shasta Street to Wickshire Street Resurfacing Project (Contract No. 23-CG0217/AP; Amount: $66,349.25)
Attachments: 1. BOCC Approval 4-23-24, 2. Contract No. 23-CG0217 Ridge Manor Road Paving Project, 3. Change Order #1, 4. Change Order #2, 5. Final Pay Packet, 6. Expenditure Status Report 1013 34602, 7. Balance Sheet by Fund 1013

TITLE

title

Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for  Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock From Shasta Street to Wickshire Street Resurfacing Project (Contract No. 23-CG0217/AP; Amount: $66,349.25)

 

body

BRIEF OVERVIEW

Final Close-Out of Contract with Goodwin Bros. Construction, Inc., for the Ridge Manor Road Paving SCOP 448504-1-54-01 Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock - SFGA project awarded by the Board on April 23, 2024, Doc Id. No. 13766, to Goodwin Bros. Construction, Inc., in the amount of $970,345.09. 

 

Change Order One (1) was requested to add Line 3 with a previous balance of $0.09, which was mistakenly closed out during rollover for new fiscal year and to add $67,348.65.  Change Order One (1) was approved by the Chief Procurement Officer (CPO) on November 12, 2024, in the amount of $67,348.74.  Purchase order was increased from $970,349.09 to $1,037,693.83.

 

Change Order Two (2) in the amount of -$314,908.74 to close out the purchase order due to project completion was approved by the CPO on April 14, 2025.  The purchase order was decreased from $1,037,693.83 to $722,785.09.

 

The Final Contract amount is $722,785.09 (PO No. 24000825). 

 

The work has been completed and Goodwin Bros. Construction, Inc., has submitted its Final Pay Application No. Five (5) in the amount of $66,349.25.

 

FINANCIAL IMPACT

Funding in the amount of $66,349.25 is available in the following accounts:

 

Expense:

 

Fund:  1013 - Constitutional Gas Tax, Department:  34602 - DPW- Ridge Manor Road Paving, Account 5616313 - Improv-Surface Treatment. Amount: $31,800.00

 

Balance Sheet: 

 

Fund:  1013 - Constitutional Gas Tax, Account:  2050067 - Retainage - Goodwin Construction: Amount: $34,549.25

 

LEGAL NOTE

The Board has the authority to act on this item pursuant to Part II, Chapter 2, Article V of the Hernando County Code of Ordinances. No notices of lien or claims of lien have been filed on the project.

 

recommendation

RECOMMENDATION

It is recommended the Board approve Final Pay Request No. Five (5) in the amount of $66,349.25 to Goodwin Bros. Construction, Inc., to close out the Ridge Manor Road Paving SCOP 448504-1-54-01 Faculty/Kedrone/Tombstone/Top Rock/Umbrella Rock - SFGA project under Contract No. 23-CG0217/AP.

 

The final contract amount is $722,785.09, a decrease of $247,560.00 from BOCC award.