Legislation Details

File #: 17762   
Type: Agenda Item Status: Adopted
File created: 7/14/2026 In control: Board of County Commissioners
On agenda: 8/11/2026 Final action: 8/11/2026
Enactment date: Enactment #:
Title: Award of Construction Contract to Goodwin Bros. Construction, Inc., for Lake Lindsey Road Resurfacing Phase 4 Project From Snow Memorial Highway to US Highway 41 a/k/a Broad Street (Contract No. 26-C01308; Amount: $1,448,463.45)
Attachments: 1. Solicitation 26-C01308, 2. Evaluation Tabulation ITB No. 26-C01308, 3. Recommendation for Award Bid No. 26-C01308, 4. Notice of Intent to Award ITB No. 26-C01308, 5. Construction Contract ITB No. 26-C01308, 6. Lake Lindsey Map, 7. 109910 Lake Lindsey, 8. 180 Exp, 9. Approved Award of Construction Contract to Goodwin Bros. Construction, Inc., for Lake Lindsey Road Resurfacing

TITLE

title

Award of Construction Contract to Goodwin Bros. Construction, Inc., for Lake Lindsey Road Resurfacing Phase 4 Project From Snow Memorial Highway to US Highway 41 a/k/a Broad Street (Contract No. 26-C01308; Amount: $1,448,463.45)

 

body

BRIEF OVERVIEW

The Procurement Department issued Invitation to Bid (ITB) No. 26-C01308 on May 27, 2026, at the request of the Hernando County Public Works Department, to obtain bids for Lake Lindsey Phase 4 Resurfacing - Snow Memorial Hwy to US 41 (Broad St).

 

The Procurement Department placed the legal advertisement in the Hernando Sun on May 29, 2026, the Tampa Bay Times on May 31, 2026, and the OpenGov website on May 27, 2026. The bid was sent to four thousand one hundred forty-five (4,145) matching vendor/contractors from the eProcurement portal. The bid document was downloaded by sixty-four (64) vendor/contractors and seven (7) submissions were received.

 

BIDs RECEIVED:

Goodwin Bros. Construction, Inc                             $1,448,463.45*

B.R.W. Contracting, Inc                                                         $1,645,649.20

Florida Asphalt Contractors LLC                                             $2,045,443.52

DB Civil Construction, LLC                                                     $2,138,358.90

Superior Asphalt, Inc                                                             $2,167,001.00

Kamminga & Roodvoets, Inc                                                  $2,298,838.90

Ajax Paving Industries of Florida, LLC                                   $2,399,108.18

 

Bids were reviewed and evaluated by the Procurement Department to determine if bids were responsive and responsible. The bids were then reviewed and evaluated by the Hernando County Public Works Department staff for award recommendation based on price, conformance with specifications and the Bidder’s ability to perform the contract in accordance with the terms, conditions and specifications required.

.

A Notice of Intent to Award the contract to Goodwin Bros. Construction, Inc dated July 21, 2026, was posted to the OpenGov website. No challenges to the Notice of Intent to Award were received.

 

The Chief Procurement Officer has reviewed this requirement for conformance to Procurement Ordinance and Purchasing Policies and Procedures.

 

STRATEGIC PLAN INITIATIVES

GOAL D.1 Well-maintained existing community assets

 

FINANCIAL IMPACT

Funding in the amount of $1,448,463.45 is available in the following:

 

Expense:

This work is part of CIP 109910-Lake Lindsey Phase 4 and is budgeted for FY2026.

 

 Fund: ADDL LOFT 1-5 Fund - B106, Department: DPW Administration - 180, Account: Capital Improv Other than Bldg - 566350, Project: Improve Pavement Mgmt - XC452

 

LEGAL NOTE

In accordance with Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended that the Board approve and authorize the Chairman’s signature on the attached construction contract to Goodwin Bros. Construction, Inc for Lake Lindsey Phase 4 Resurfacing - Snow Memorial Hwy to US 41 (Broad St), (Contract No. 26-C01308) in the bid amount of $1,448,463.45.

 

It is further recommended the Board authorize the Chief Procurement Office to approve change orders as necessary and required up to budgeted amounts.