File #: 14511   
Type: Resolution Status: Adopted
File created: 8/23/2024 In control: Board of County Commissioners
On agenda: 11/19/2024 Final action: 11/19/2024
Enactment date: 11/19/2024 Enactment #:
Title: Award of Construction Contract to Midsouth, Inc., for Septic to Sewer Conversion District A Phase 1 and Associated Budget Resolution (Contract No. 24-CG00768/JG; Amount: $15,553,016.11)
Attachments: 1. Solicitation for 24-CG00768-JG, 2. Midsouth, Inc., Response, 3. Evaluation Bid Tab, 4. Department Letter of Recommendation - Midsouth 10 04 2024.pdf, 5. Anti Human Trafficking Affidavit- MIDSOUTH.pdf, 6. Notice of Intent to Award, 7. Construction Contract for 24-CG00768-JG, 8. Budget Resolution - HCUD Capital Grt 33595, 9. Expenditure Status Report 4144 33505, 10. Approved Award of Construction Contract to Midsouth, Inc., for Septic to Sewer Conversion District A Phase 1, 11. Approved Budget Resolution 2024-246

TITLE

title

Award of Construction Contract to Midsouth, Inc., for Septic to Sewer Conversion District A Phase 1 and Associated Budget Resolution (Contract No. 24-CG00768/JG; Amount: $15,553,016.11)

 

body

BRIEF OVERVIEW

At the request of the Hernando County Utilities Department (HCUD), the Procurement Department issued Invitation to Bid (ITB) No. 24-CG00768/JG on June 12, 2024, to obtain bids for the Septic to Sewer Conversion District A Phase 1 Project.

 

Procurement staff placed the legal advertisement in the Tampa Bay Times and the Hernando Sun on June 5, 2024, and the OpenGov website on June 12, 2024. The bid was sent to three thousand two hundred twenty-three (3,223) matching vendor/contractors from the website. The bid document was downloaded by seventy-four (74) vendor/contractors and one (1) bid submission was received.

 

BID RECEIVED:

 

                     Midsouth, Inc., Bushnell, FL                      $30,809,233.90

 

Bid was reviewed and evaluated by the Procurement Department to determine if bid was responsive and responsible. The bid was then reviewed and evaluated by HCUD staff for award recommendation based on price, conformance with specifications and the Bidder’s ability to perform the contract in accordance with the terms, conditions and specifications required.

 

HCUD requested a partial award for Sewershed No. 2 and Sewershed No. 6 only.

 

A Notice of Intent to Award the contract to Midsouth, Inc., dated September 23, 2024, was posted to the OpenGov website and posted to the Hernando County Administration electronic public bulletin board.

 

As this solicitation received one (1) bid and as this is a federally funded grant project, 2 CFR 200 requires negotiation of profit as a separate line item. County staff initiated negotiations on October 4, 2024, and concluded on October 16, 2024, resulting in a new total contract amount of $15,553,016.11.

 

The Chief Procurement Officer has reviewed this requirement for conformance to Procurement Ordinance and Purchasing Policies and Procedures.

 

FINANCIAL IMPACT

Project is ARPA and FDEP funded as follows:

Fund:  4144 - HCUD Capital, Department:  33595 - SLFRF - Septic to Sewer PH1, Account:  5626322 - Improv-Sewer Line Upgrade in the amount of $6,052,821.00 (ARPA Funds)

Fund:  4144 - HCUD Capital, Department:  33505 - HUCD-Septic to Sewer PH1- Account:  5626322 - Improv-Sewer Line Upgrade (FDEP Funds)

 

An associated budget resolution for Fund:  4144 - HCUD Capital, Department:  33595 - SLFRF - Septic to Sewer PH1 is attached for the Board’s approval. Funding in Fund:  4144 - HCUD Capital, Department:  33505 - HUCD-Septic to Sewer PH1 is currently available.

 

LEGAL NOTE

In accordance with Part II, Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended that the Board approve award and authorize the Chairman’s signature on the attached Construction Agreement to Midsouth, Inc., for the Septic to Sewer Conversion District A Phase 1 (Contract No. 24-CG00768/JG) for the total amount of $15,553,016.11 for Sewer Shed No. 2 and for Sewer Shed No. 6; and, approve and authorize the Chaiman’s signature on the attached associated budget resolution recognizing the ARPA funding.

 

It is further recommended the Board authorize the Chief Procurement Officer to approve change orders as they become necessary and required up to budgeted amounts.