Title: Change Order No. 6 to Purchase Order With McKim & Creed, Inc., for Chalmer Pumping Station Upgrade Project for Utilities Department (Contract No. 18-R00020; Amount: $59,616.00)
Attachments: 1. 18-R00020 BOCC Approval, 2. 18-R00020A Contract - McKim & Creed, 3. 18-R00020A McKim & Creed - Award Letter, 4. 18-R00020 Award Renewal - McKimCreed - 7.9.2022, 5. 18-R00020 Award Renewal - McKimCreed 7.9.2023, 6. Interim Extension Letter - 18-R00020 McKim Creed, 7. Task Order 7 Scope and Fee, 8. Purchase Order 21000814, 9. Change Order No. 1, 10. Change Order No. 2, 11. Change Order No. 3, 12. Change Order No. 4, 13. Change Order No. 5, 14. Change Order No. 6
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

title

Change Order No. 6 to Purchase Order With McKim & Creed, Inc., for Chalmer Pumping Station Upgrade Project for Utilities Department (Contract No. 18-R00020; Amount: $59,616.00)

 

body

BRIEF OVERVIEW

On July 10, 2018, the BOCC approved award of Contract No. 18-R00020 to McKim & Creed, Inc. for the Continuing Engineering Services for Water, Wastewater and Reclaimed Water Projects.

 

On April 28, 2021, the Chief Procurement Officer (CPO) approved Task Order No. 7 for Chalmer Pumping Station Upgrade.

 

The purchase order was originally issued for $281,286.79. Change order No. 6 in the amount of $59,616.00, would increase the Purchase Order to $553,577.83.

 

Change Order No. 1, a no cost time extension, was CPO approved on March 4, 2022, to complete design phase of project.

 

Change Order No. 2 in the amount of $7,378.25 was CPO approved on March 15, 2023, to ensure the force main is sized properly for additional flow.

 

Change Order No. 3 in the amount of $19,037.31 was CPO approved on August 14, 2023, to change the design from a 10” FM to a 12” FM to accommodate flows from the Somerset Bay subdivision.

 

Change Order No. 4 in the amount of $13,936.78, was CPO approved on October 4, 2023, and necessary due to FDEP requiring a flow meter to be located at any new construction lift station with a design pump rate above 350 GPM. 

 

Change Order No. 5 in the amount of $172,322.70, was CPO approved on December 13, 2024, for additional daily inspection services to this project.

 

Hernando County Utilities Department has requested an increase for Purchase Order No. 21000814 for additional funding and 432 labor hours to ensure CEI support through the project completion date of May 17, 2026, per scope of work.  This constitutes Changer Order No. 6 in the amount of $59,616.00.

 

STRATEGIC PLAN INITIATIVES

NA

 

FINANCIAL IMPACT

Funding in the amount of $59,616.00 is available in the following:

B411-200-14102-40-53600-566350-XC554

 

Expense:

 

Fund: HCUD-Water &Sewer Fund - B411, Department: HCUD Administration - 200, Account: Capital Improvement Other Than Building - 566350

 

LEGAL NOTE

The Board has the authority to act on this item pursuant to Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended the Board approve Change Order No. 6 in the amount of $59,616.00 to McKim & Creed, Inc. for Purchase Order No. 21000814, bringing the total Purchase Order amount to $553,577.83.

 

It is further recommended the Board authorize the Chief Procurement Officer to approve change orders, as necessary and required up to the allowable budgeted amount.