File #: 17251   
Type: Agenda Item Status: Agenda Ready
File created: 3/2/2026 In control: Board of County Commissioners
On agenda: 5/26/2026 Final action:
Enactment date: Enactment #:
Title: Letter of Understanding With Florida Department of Transportation and Pasco County for County Line Road Widening Project Located East of Mariner Boulevard to West of Suncoast Parkway a/k/a State Road 589
Attachments: 1. Letter of Understanding for County Line Road Widening, 2. County Line Road - Marnier Blvd to Suncoast Parkway Map, 3. Approved Letter of Understanding With Florida Department of Transportation and Pasco County for County Line Road Widening Project

TITLE

title

Letter of Understanding With Florida Department of Transportation and Pasco County for County Line Road Widening Project Located East of Mariner Boulevard to West of Suncoast Parkway a/k/a State Road 589

 

body

BRIEF OVERVIEW

The Florida Department of Transportation (FDOT) is currently in the design phase for widening County Line Road (FPID: 257298-7) from two lanes to four lanes between Hernando and Pasco Counties from east of Mariner Boulevard to west of the Suncoast Parkway (SR589).  As FDOT, Hernando County and Pasco County continue to collaborate on this project, there are several elements that require coordination and assurances from both FDOT and the counties.  The purpose of the proposed Letter of Understanding is to confirm the understanding between FDOT and the counties concerning roadway improvements to be made to County Line Road.

 

FDOT has estimated right-of-way costs to be $20,000,000. Each county will provide $5,000,000 to FDOT through a locally funded agreement on or before July 1, 2028. FDOT will provide matching resources in the amount of $10,000,000 subject to legislative appropriation.

 

FDOT has estimated construction costs to be approximately $65,000,000. Construction will be funded in the manner listed below:

 

a.                     Each COUNTY will provide the FDOT $5,000,000 through a locally funded agreement on or before July 1, 2030. FDOT will provide matching resources in the amount of $10,000,000, subject to legislative appropriation.

 

b.                     FDOT proposes to secure a State Infrastructure Bank loan for the remaining construction funding, subject to legislative appropriation. Each county will be responsible for one half of the loan repayment funds, the term of which will be determined prior to the advertising of FDOT’s construction contract.

 

FINANCIAL IMPACT

There is no current Financial Impact for this Letter of Understanding.  FDOT will provide a locally funded agreement on or before July 1, 2028, for right-of-way acquisition.  A locally funded agreement for construction costs will be provided on or before July 1, 2030.  These agreements will be presented to the Board at those times.

 

The required County funding for 2028 and 2030 has been entered into the FY 27 CIP.

 

LEGAL NOTE

The Board is authorized to act on this matter pursuant to Chapter 125, Florida Statutes.

 

recommendation

RECOMMENDATION

It is recommended the Board approve and authorize the Chairperson’s signature on the attached Letter of Understanding for the County Line Road widening project.