File #: 16246   
Type: Agenda Item Status: Agenda Ready
File created: 7/28/2025 In control: Board of County Commissioners
On agenda: 8/26/2025 Final action:
Enactment date: Enactment #:
Title: Change Order No. 5 to Purchase Order With Coastal Engineering Associates, Inc., for Engineering Services for Septic to Sewer Conversion, District A Project and Development of Septic Upgrade Incentive Program for Utilities Department (Contract No. 21-RG0045; Amount: $120,857.00)
Attachments: 1. BOCC Approval 10878, 2. Contract No. 21-RG0045/PH - 08.23.2022, 3. Amendment No. 1 - Approved 05.23.2023, 4. Executed Amendment 2, 5. Change Order #1 - 02.23.2023, 6. Change Order #2 - 08.09.2023, 7. Change Order #3 - 04.15.2024, 8. Change Order #4 - 01-06.2025, 9. Change Order #5 - $120,857.00, 10. Expenditure Status Report 4144
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TITLE

title

Change Order No. 5 to Purchase Order With Coastal Engineering Associates, Inc., for Engineering Services for Septic to Sewer Conversion, District A Project and Development of Septic Upgrade Incentive Program for Utilities Department (Contract No. 21-RG0045; Amount: $120,857.00)

 

body

BRIEF OVERVIEW

On August 23,2022, the BOCC approved award of Contract No. 21-RG0045 to Coastal Engineering Associates, Inc., for the Engineering Services for Septic to Sewer Conversion, District A for $2,097,218.00.

 

The purchase order was originally issued for $1,798,678.  Change Order No. 5 in the amount of $120,857.00, would increase the purchase order to $2,497,604.00.

 

Change Order No. 1 in the amount of $2,000.00 was approved by the Chief Procurement Officer (CPO) on February 23, 2023, for additional landowner letter mailings and increased postal costs.

 

Change Order No. 2 in the amount of $8,584.00 was approved by the CPO on August 9, 2023, for a relocated Force Main connection at Winn Dixie which required additional surveying not included in original scope.

 

Change Order No. 3 in the amount of $28,310.00 was approved by the CPO on April 15, 2024, for modifying plans to allow for less intrusive construction method.

 

Change Order No. 4 in the amount of $539,175.00 was approved by the Board on November 19, 2024, to allow for construction engineering services to be completed by engineer for the duration of the construction project which was extended to 474 days.

 

Hernando County Utilities Department has requested an increase to Purchase Order No. 22001066 to add hours for Engineer for Record to assist with Davis Bacon Act reporting requirements and Domestic Preference compliance review.

 

FINANCIAL IMPACT

Funding in the amount of $120,857.00 is available in:

 

Fund:  4144 - HCUD - Capital, Department:  33505 - HCUD-Septic to Sewer PH1, Account:  5626322 - Improv-Sewer Line Upgrade

 

LEGAL NOTE

The Board has the authority to act on this item pursuant to Part II, Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended the Board approve Change Order No. 5 in the amount of $120,857.00 to Coastal Engineering Associates, Inc., for Purchase Order No. 22001066, bringing the total purchase order amount to $2,497,604.00.