Hernando County, FL Banner Image
File #: 12590   
Type: Agenda Item Status: Adopted
File created: 7/25/2023 In control: Board of County Commissioners
On agenda: 8/22/2023 Final action: 8/22/2023
Enactment date: Enactment #:
Title: Final Close-Out of Contract With Goodwin Bros Construction, Inc., for English Sparrow Road and Eskimo Curlew Road Resurfacing Project (Contract No. 22-C00127/DK; Amount: $39,137.68)
Attachments: 1. Construction Agreement 11.29.2022, 2. Final Pay for PO No. 23000490

TITLE

title

Final Close-Out of Contract With Goodwin Bros Construction, Inc., for English Sparrow Road and Eskimo Curlew Road Resurfacing Project (Contract No. 22-C00127/DK; Amount: $39,137.68)

 

body

BRIEF OVERVIEW

Final Close-Out of Contract with Goodwin Bros Construction, Inc., for English Sparrow and Eskimo Curlew Resurfacing Project awarded by the Board on November 29, 2022, Doc Id. No. 11375, to Goodwin Bros Construction., in the amount of $788,398.08. 

 

Change Order One (1) was to increase purchase order due to additional materials and work request due to unknown buried culvert damaged when mixing the road for the stabilized subgrade.  Total increase was for $15,335.52.  Purchase order was increased from $788,398.08 to $803,733.60.

 

Change Order Two (2) will be completed after Final Pay packet is posted.  Encumbrance balance is currently not sufficient to decrease Line1 Project Code 110930 by $59,118.82, during final pay process a credit will be applied to Line 1 Project Code 110930 that will allow for the change order to be processed in Finance Plus.  The change order will decrease the purchase order in the amount of $146,371.05 and close out the purchase order.  Purchase order will decrease from $803,733.60 to $657,362.55.

 

The Final Contract amount is $657,362.55 (PO No. 23000490). 

 

The work has been completed and Goodwin Bros Construction, Inc., has submitted its Final Pay Application No. Four (4) in the amount of $39,137.68.

 

All releases properly include Hernando County.  Goodwin Bros Construction, Inc., has signed a release of lien.  No notices of lien or claims of lien have been filed on the project.

 

FINANCIAL IMPACT

Funding in the amount of $39,137.68 is available in the following accounts:  Account No. 1013-03211-5616313 (Debt Srv/Reserv-Const GT - Improv-Surface Treatment in the amount of $6,599.53 and Retainage Account No. 1013-2050067 (Constitutional Gas Tax, Retainage - Goodwin Construction) in the amount of $32,538.15.

 

LEGAL NOTE

The Board has the authority to take the recommended action on this item pursuant to Chapter 125, Florida Statutes. 

 

recommendation

RECOMMENDATION

It is recommended the Board approve final pay Request No. Four (4) in the amount of $39,137.68 to Goodwin Bros Construction, Inc., to close out the English Sparrow and Eskimo Curlew Resurfacing Project under Contract No. 22-C00127/DK.

 

The Final Contract amount is $657,362.55, a decrease of $131,035.53 from BOCC award.