Legislation Details

File #: 17645   
Type: Agenda Item Status: Agenda Ready
File created: 6/12/2026 In control: Board of County Commissioners
On agenda: 7/14/2026 Final action:
Enactment date: Enactment #:
Title: Change Order No. 6 to Purchase Order With Coastal Engineering Associates, Inc., for Engineering Services for Septic to Sewer Conversion, District A Project and Development of Septic Upgrade Incentive Program for Utilities Department (Contract No. 21-RG0045; Amount: $2,037,026.00)
Attachments: 1. Executed Contract No. 21-R0045, 2. Amendment No. 1 & BOCC Approval, 3. Amendment No. 2, 4. Change Order #1, 5. Change Order #2, 6. Change Order #3, 7. Change Order #4 & BOCC Approval, 8. Change Order #5 & BOCC Approval, 9. Change Order # 6, 10. 412 Exp

 

TITLE

title

Change Order No. 6 to Purchase Order With Coastal Engineering Associates, Inc., for Engineering Services for Septic to Sewer Conversion, District A Project and Development of Septic Upgrade Incentive Program for Utilities Department (Contract No. 21-RG0045; Amount: $2,037,026.00)

 

body

BRIEF OVERVIEW

On August 23,2022, the BOCC approved award of Contract No. 21-RG0045 to Coastal Engineering Associates, Inc., for the Engineering Services for Septic to Sewer Conversion, District A for $2,097,218.00.

 

The purchase order was originally issued for $1,798,678.  Change Order No. 6 in the amount of $2,037,026.00, would increase the purchase order to $4,534,630.00.

 

Change Order No. 1 in the amount of $2,000.00 was approved by the Chief Procurement Officer (CPO) on February 23, 2023, for additional landowner letter mailings and increased postal costs.

 

Change Order No. 2 in the amount of $8,584.00 was approved by the CPO on August 9, 2023, for a relocated Force Main connection at Winn Dixie which required additional surveying not included in original scope.

 

Change Order No. 3 in the amount of $28,310.00 was approved by the CPO on April 15, 2024, for modifying plans to allow for less intrusive construction method.

 

Change Order No. 4 in the amount of $539,175.00 was approved by the Board on November 19, 2024, to allow for construction engineering services to be completed by engineer for the duration of the construction project which was extended to 474 days.

 

Change Order No. 5 in the amount of $120,857.00, was approved by the Board on August 26, 2025, to add hours for Engineer of Record to assist with Davis Bacon Act reporting requirements and Domestic Preference compliance review.

 

The request from Hernando County Utilities to increase Purchase Order No. 22001066 in the amount of $2,037,026.00 for Coastal Engineering Associates is two-fold:

                     Final design services, permitting and engineering services portion of the Construction Contract Administration during the construction phase of District A Phase 1 Sewershed 5 in the amount of $399,122.00

                     Final detailed design services for the gravity sewer system, pump station, forcemain and lot connections to provide sanitary sewer service for District A Phase 2 in the amount of $1,637,904.00.

 

 

FINANCIAL IMPACT

Grant Funding in the amount of $2,037,026.00 is available in:

 

Expense:

 

Fund:  HCUD-Water&Sewer Grant Fund - B412, Department: HCUD-Administration - 200, Groups: HCUD-Septic to Sewer PH1 - 30043, Account:  Capital Improve other than BLDG - 566350, Project: Improv-Sewer Line Upgrade - XC553

 

LEGAL NOTE

The Board has the authority to act on this item pursuant to Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended the Board approve Change Order No. 6 in the amount of $2,037,026.00 to Coastal Engineering Associates, Inc., for Purchase Order No. 22001066, bringing the total purchase order amount to $4,534,630.00.

.