TITLE
title
Signatory Authorization to Utilities Director to Execute and Record Temporary Construction Easements for Septic to Sewer Project
body
BRIEF OVERVIEW
The Hernando County Water & Sewer District (District) plans to construct and install new and updated sewer system in the County right-of-way in front of properties within the boundaries of the septic to sewer conversion project. The project will require decommissioning of the existing septic tank on each property, installing a new sewer service line to the property from the new sewer system to the house or building on the property, and connection of the new sewer service line to the new gravity sewer line in the road right-of-way. A Temporary Construction Easement form has been prepared for execution by the record owner of each parcel of affected property.
In an effort to expedite the time for processing and recording the documents, staff requests that the Utilities Director be granted the authority to execute and record each of the easements on behalf of the District as they are returned by the property owners.
FINANCIAL IMPACT
N/A
LEGAL NOTE
The Board is authorized to act upon this matter pursuant to Chapter 125, Florida Statutes.
recommendation
RECOMMENDATION
It is recommended that the Board approve and authorize the Chairman’s signature on the attached resolution to accommodate decommissioning of septic tanks and connection of sewer lines for the Septic to Sewer Project. It is further recommended that the Board authorize and approve the Utilities Director to sign and record the Temporary Construction Easements on behalf of the District.