Legislation Details

File #: 18131   
Type: Agenda Item Status: Agenda Ready
File created: 10/20/2026 In control: Board of County Commissioners
On agenda: 11/17/2026 Final action:
Enactment date: Enactment #:
Title: Change Order No. 1 to Purchase Order With HDR Engineering, Inc., for Barclay Avenue Intersection Improvement Project Phase 1 Located State Road 50 to Lucky Lane for Department of Public Works (Contract No. 23-RFQ00422 TO #02; Amount of Change Order: $336,480.17)
Attachments: 1. Contract No. 23-RFQ00422 Continuing Professional Engineering Services, 2. BOCC Approval No. 13852 on 6-25-24, 3. Amendment No. 1, 4. Task Order No. 2, 5. Purchase Order No. 24001034, 6. Changer Order No. 1, 7. Barclay Ave SR50 to Lucky Lane Location Map, 8. 335 Exp
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
title
Change Order No. 1 to Purchase Order With HDR Engineering, Inc., for Barclay Avenue Intersection Improvement Project Phase 1 Located State Road 50 to Lucky Lane for Department of Public Works (Contract No. 23-RFQ00422 TO #02; Amount of Change Order: $336,480.17)

body
BRIEF OVERVIEW
On June 25, 2024, the BOCC approved award of Contract No.23-RFQ00422 to Coastal Engineering Associates, Inc.; HDR Engineering, Inc.; Ayres Associates, Inc.; Infrastructure Consulting & Engineering, PLLC; and Jones Edmunds & Associates, Inc., for Continuing Professional Engineering Services

On September 9, 2024, the Chief Procurement Officer approved Task Order No. 2 for Barclay Ave from SR50 to Lucky Lane Phase 1 Intersection Improvements to HDR Engineering, Inc.

The purchase order was originally issued for $499,709.83. Change order No. 1 in the amount of $336,480.17, would increase the Purchase Order to $836,190.00.

Hernando County Public Works Department has requested an increase for Purchase Order No. 24001034 for changes being made to original project design to accommodate the changes needed on bike trail, utility relocation plans, and curbing.

STRATEGIC PLAN INITIATIVES
Strategic Theme: D – Quality of Life
Goal D.1 Well Maintained existing community assets

FINANCIAL IMPACT
Funding in the amount of $399,480.17 is available in the following:

Expense:

Fund: Impact Fee-Road - B335; Department: DPW-Admin -180; Group: IF-Road Dist 4 -13104; Account: Capital-Improve Other than BLDG – 566350

CIP 112075 - Barclay Ave Widening Utility Improvement Phase 1, included in the approved FY 27 CIP.

LEGAL NOTE
The Board has the authority to act on this item pursuant to Chapter 2, Article V of the Hernando County Code of Ordinances.

recommendation
RECOMMENDATION
It is recommended the Board approve Change Order No. 1 in the amount of $336,480.17 to HDR Engineering, Inc. for Purchase Order No. 24001034, bringing the total Purchase Order amount to $836,190.00.

It is further re...

Click here for full text