Hernando County, FL Banner Image
File #: 11573   
Type: Agenda Item Status: Adopted
File created: 12/16/2022 In control: Board of County Commissioners
On agenda: 1/10/2023 Final action: 1/10/2023
Enactment date: Enactment #:
Title: Ratification of Change Order No. 1 to Purchase Order to Goodwin Bros. Construction, Inc., for Concrete Work at Solid Waste and Recycling Department West Convenience Center and Associated Budget Amendment (Contract No. 19-R00007-58; Amount: $107,040.00)
Attachments: 1. Change Order 1, 2. Original Project Approval, 3. Budget Amendment
TITLE
title
Ratification of Change Order No. 1 to Purchase Order to Goodwin Bros. Construction, Inc., for Concrete Work at Solid Waste and Recycling Department West Convenience Center and Associated Budget Amendment (Contract No. 19-R00007-58; Amount: $107,040.00)

body
BRIEF OVERVIEW
On December 14, 2021, (BOCC Doc Id No.19083) the Boar approved Quote No. 58 under Contract 19-R00007 Construction Services Under $200K, to Goodwin Bros. Construction Inc., in the amount of $197,621.54.

The West Convenience Center awarded concrete work was comprised of pouring a pad on the north side of the ramp, pouring two vertical cap walls where trailers are backed into place and pouring new concrete for three (3) chutes that are located on the ramp.

Hernando County Solid Waste and Recycling requested additional work resulting in Change Order 1. This involved excavation and grade correction to the swales which had not been addressed in several years, installation of dock bumpers to protect the new concrete walls from being hit by roll off boxes, chute rebuilding due to age and installation of a more stable loading ramp for mulch loading. These repairs and improvements resulted in additional work in the amount of $107,040.00.

Change Order One (1) was processed before Board approval based upon the immediate need for services to be performed. The additional work increased the project by $107,040.00 for a new project total of $304,661.54.

The additional $107,040.00 was not budgeted for this project and staff is requesting the attached budget amendment be approved so funds are available for the change order.

FINANCIAL IMPACT
Funds are available from Hernando County Solid Waste and Recycling Budget Line Item 07691-5626301 Solid Waste/Recyc-Capital, Improv (Grtr than 10,000.00) in the amount of $107,040.00.