Legislation Details

File #: 17489   
Type: Agenda Item Status: Agenda Ready
File created: 5/5/2026 In control: Board of County Commissioners
On agenda: 5/26/2026 Final action:
Enactment date: Enactment #:
Title: Proposed Award of Contract to Ayres Associates Inc for Barclay Avenue Roadway Improvements from Powell Road to Lucky Lane Design (Contract No. 25-RFQ01076/FH; Amount: $6,414,280.58).
Attachments: 1. Solicitation - Barclay Design Phase II, 2. Proposal - Ayres, 3. References - Ayres, 4. Committee's Evaluation Summary, 5. Contract No. 25-RFQ01076/FH - Notice of Intent to Award, 6. Contract No. 25-RFQ01076/FH - Profesional Service Agreement, 7. Barclay Location Maps, 8. Budget Amendment 80497
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
title
Proposed Award of Contract to Ayres Associates Inc for Barclay Avenue Roadway Improvements from Powell Road to Lucky Lane Design (Contract No. 25-RFQ01076/FH; Amount: $6,414,280.58).

body
BRIEF OVERVIEW
The Procurement Department issued Request for Qualifications (RFQ) No. 25RFQ01076/FH on October 8, 2025, at the request of the Hernando County Public Works Department for design of Barclay Avenue roadway improvements from Powell Road to Lucky Lane.

The Procurement Department placed the legal advertisement in the Hernando Sun on October 10, 2025, and the OpenGov website on October 8, 2025. The solicitation was sent to three thousand eight hundred sixty-eight (3,868) matching vendor/contractors from the website. The solicitation document was downloaded by one hundred one (101) contractors and seven (7) submissions were received.

The Procurement Department reviewed and evaluated submissions to determine if submissions were responsive and responsible. The Procurement Selection Committee (PSC) met on January 9, 2026 to evaluate the proposals. The committee included Scott Herring, Public Works Director; Erik Van De Boogard, Construction Projects Coordinator; Todd Crosby, Assistant County Engineer; Kelly Soreng, Real Property Supervisor; and, Josh Walker, Project Manager (Utilities). The PSC consensus scoring evaluation resulted in the following scores:

Firm Total Score (Max Score: 100)
Mead & Hunt, Inc. 85.4
HDR Engineering, Inc. 84.6
Ayres Associates, Inc. 84.4
DRMP, Inc. 83.2
Stantec Consulting Services, Inc. 81.4
Kimley-Horn and Associates, Inc. 81.0
LJA Engineering Inc. 77.6

The PSC requested to proceed with oral presentations, which were conducted on February 4, 2026, with the top three (3) ranked firms. The PSC consensus scoring resulted in the following total consensus scores:

Firm Total Score (Max Score: 120)
Ayres Associates Inc 102.4
Mead & Hunt, Inc. 100.2
HDR Engineering, Inc. 96.8