Hernando County, FL Banner Image
File #: 12773   
Type: Agenda Item Status: Agenda Ready
File created: 9/1/2023 In control: Board of County Commissioners
On agenda: 10/10/2023 Final action:
Enactment date: Enactment #:
Title: Amendment No. 1 to Contract With Straughn Trout Architects for Architectural and Engineering Services for Tax Collector Building (Contract No. 21-RFQ-AE-016; Amount: $373,926.50)
Attachments: 1. A/E Agreement - Architect/Engineering Services for Tax Collector Building, 2. BOCC Approval 11-29-22, 3. Additional Services Request, 4. Amendment No 1 to Contract No. 21-RFQ-AE-016
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
title
Amendment No. 1 to Contract With Straughn Trout Architects for Architectural and Engineering Services for Tax Collector Building (Contract No. 21-RFQ-AE-016; Amount: $373,926.50)

body
BRIEF OVERVIEW
On November 29, 2022, the Board approved the award of Contract to Straughn Trout Architects for Architectural and Engineering Services for the Tax Collector Building in the amount of $11,300,000 with Professional Services itemized at $1,457,621.00 which included Ecological Services-Gopher Tortoise Services in the amount of $162,940.00.

On January 24, 2023, an initial 100% site census survey was conducted and located 143 gopher tortoise burrows. Of the 143 burrows, 136 were identified as potentially occupied, and seven were identified as abandoned.

Prior to initiating gopher tortoise relocation, Task 103 requires additional services to accommodate the number of gopher tortoises and burrows encountered upon completion of the survey. The request for services update for Task 103 is to provide additional funding to complete the activities required for the census, permitting, and relocation of gopher tortoises (Gopherus polyphemus) from the project site in accordance with the Florida Fish and Wildlife Conservation Commission (FWC) Gopher Tortoise Permitting Guidelines (FWC 2020).

Services requested for Task 103:

Second Census Task for Gopher Tortoise Burrow Survey $ 4,301.00
Design Fee Permit Application $ 11,500.00
Permit Fee $ 23,283.00
Gopher Tortoise Relocation $ 78,832.50
Recipient Site Fee $418,950.00
TOTAL: $536,866.50

It is requested that the Board approve the additional services for Task 3 and increase funding for Professional Services from $1,457,621.00 to $1,994,487.50 in the amount of $373,926.50. $536,866.50 less previously approved $162,940.00 = $373,926.50.

FINANCIAL IMPACT
The Combined Tax Collector Annex Contracts Contract #2021-RFP-GMGC-015-TB and #2021-RFQ-AE-016-TB have total funding in the amount of $15,000,000.00. Funding...

Click here for full text