File #: 11163   
Type: Agenda Item Status: Adopted
File created: 10/5/2022 In control: Board of County Commissioners
On agenda: 11/8/2022 Final action: 11/8/2022
Enactment date: Enactment #:
Title: Final Close-Out of Contract With David Nelson Construction Co., for US 19 at Forest Oaks Boulevard Intersection Improvement Project (Contract No. 21-C00121/DK; Amount: $31,425.02)
Attachments: 1. Pay Req #5

TITLE

title

Final Close-Out of Contract With David Nelson Construction Co., for US 19 at Forest Oaks Boulevard Intersection Improvement Project (Contract No. 21-C00121/DK; Amount: $31,425.02)

 

body

BRIEF OVERVIEW

The US 19 and Forest Oaks Boulevard Intersection Improvement Project was awarded by the Board on November 16, 2021, Doc. Id. No. 18961, to David Nelson Construction Co. in the amount of $647,678.50.

 

Change Order No. One (1) was for 50 Linear Feet of replacement curbing, increasing the Contract by $2,000.00 from $647,678.50 to $649,678.50.

 

Change Order No. Two (2) was a reduction of materials to actual used, decreasing the Contract by $21,178.09 from $649,678.50 to $628,500.41.

 

The Final Contract amount is $628,500.41 (PO No. 22000453).

 

The work has been completed and David Nelson Construction Co., has submitted its Final Pay Application No. Five (5) in the amount of $31,425.02.

 

FINANCIAL IMPACT

Funding in the amount of $31,425.02 is available in Retainage Account 3334-2050227 Impact Fee - Road Dist #4, Retainage.

 

LEGAL NOTE

Legal Authority under F.S. Chapter 125 (All releases properly include Hernando County).

 

recommendation

RECOMMENDATION

It is recommended the Board approve final pay request No. Five (5) in the amount of $31,425.02 to David Nelson Construction Co., to close out Contract No. 21-C00121/DK for US 19 and Forest Oaks Boulevard Intersection Improvement Project.

 

The final Contract amount for this unit is $628,500.41, a Contract decrease of $19,178.09 to BOCC award.