Final Close-Out of Contract With David Nelson Construction Co., for US 19 at Forest Oaks Boulevard Intersection Improvement Project (Contract No. 21-C00121/DK; Amount: $31,425.02)
body
BRIEF OVERVIEW
The US 19 and Forest Oaks Boulevard Intersection Improvement Project was awarded by the Board on November 16, 2021, Doc. Id. No. 18961, to David Nelson Construction Co. in the amount of $647,678.50.
Change Order No. One (1) was for 50 Linear Feet of replacement curbing, increasing the Contract by $2,000.00 from $647,678.50 to $649,678.50.
Change Order No. Two (2) was a reduction of materials to actual used, decreasing the Contract by $21,178.09 from $649,678.50 to $628,500.41.
The Final Contract amount is $628,500.41 (PO No. 22000453).
The work has been completed and David Nelson Construction Co., has submitted its Final Pay Application No. Five (5) in the amount of $31,425.02.
FINANCIAL IMPACT
Funding in the amount of $31,425.02 is available in Retainage Account 3334-2050227 Impact Fee - Road Dist #4, Retainage.
LEGAL NOTE
Legal Authority under F.S. Chapter 125 (All releases properly include Hernando County).
recommendation
RECOMMENDATION
It is recommended the Board approve final pay request No. Five (5) in the amount of $31,425.02 to David Nelson Construction Co., to close out Contract No. 21-C00121/DK for US 19 and Forest Oaks Boulevard Intersection Improvement Project.
The final Contract amount for this unit is $628,500.41, a Contract decrease of $19,178.09 to BOCC award.