File #: 14029   
Type: Agenda Item Status: Adopted
File created: 5/3/2024 In control: Board of County Commissioners
On agenda: 5/28/2024 Final action: 5/28/2024
Enactment date: Enactment #:
Title: Final Close-Out of Contract With Augustine Construction, Inc., for Construction for Elgin Boulevard Sidewalk Local Agency Program Project From Deltona Boulevard to Mariner Boulevard (Contract No. 22-CG0039/DK; Amount: $124,349.93)
Attachments: 1. 22-CG0039 Contract, 2. Elgin Boulevard - Deltona to Mariner Aerial, 3. Final Pay Packet, 4. Balance Sheet 1013, 5. Expenditure Status Report 1013 03211
TITLE
title
Final Close-Out of Contract With Augustine Construction, Inc., for Construction for Elgin Boulevard Sidewalk Local Agency Program Project From Deltona Boulevard to Mariner Boulevard (Contract No. 22-CG0039/DK; Amount: $124,349.93)

body
BRIEF OVERVIEW
Construction for Elgin Boulevard Sidewalk Local Agency Program Project from Deltona Boulevard to Mariner Boulevard was awarded by the Board on July 26, 2022, Doc Id. No. 10726, to Augustine Construction, Inc., in the amount of $1,206,337.04.

Change Order One (1) was to invert the funding information in Finance Plus. This is an administrative function no change to purchase order amount.

Change Order Two (2) was to increase the purchase order by $72,402.14 for additional work needed due to field changes and to extend Final Completion date to November 26, 2023. Change increased the contract by $72,402.14 from $1,206,337.04 to $1,278,739.18.

Change Order Three (3) was to increase the purchase order by $40,731.66 for additional work to address existing drainage concerns and to extend Final Completion date 14 days to December 10, 2023. Change increased the contract by $40,731.66 from $1,278,739.18 to $1,319,470.84.

Change Order Four (4) was to decrease the purchase order by $0.52 for removing of items determined not needed and additional changes to work needed. Time extended for Final Completion date by 14 days to December 24, 2023. Change decreased the contract by $0.52 from $1, 319,470.84 to $1,319,470.32.

Change Order Five (5) was for a no-cost time extension due to additional field changes. Time extended for Final Completion date by 10 days to January 3, 2024.

Change Order Six (6) was for a no-cost time extension for production and installation of signage and for final close out work. Time extended for Final Completion date by 21 days to January 24, 2024.

Change Order Seven (7) was to decrease the purchase order by $114,669.00 per the Schedule of Values. Change order decreasing the Contract...