Amendment No. 1 to Grant Agreement With State Department of Environmental Protection for Northcliffe Boulevard Force Main Project
body
BRIEF OVERVIEW
The Grant Agreement (No. WG026) between the Florida Department of Environmental Protection (FDEP) and Hernando County was approved by the BOCC on October 11, 2022, (LS 10969). Change Order No. 1 to Grant Agreement WT026 shifting the funding from State and Local Fiscal Recovery Funds (SLFRF) to State Funding was approved by BOCC on August 27, 2024, (LS14371).
Amendment 1 was originally submitted to BOCC and approved on November 19, 2024, (LS14811); however, an adjustment is needed to increase the preconstruction activities task grant amount from $70,464.00 to $84,127.23 and reduce the project management activities grant amount from $29,536.00 to $15,872.77. Therefore, attached is an updated Amendment 1 with the following changes requested by Hernando County and agreed upon by FDEP:
1. A revision in the scope of work and a budget reallocation for the project.
2. Addition of a new task to the grant work plan.
The total amount of grant funding remains unchanged.
FINANCIAL IMPACT
There is no financial impact resulting from this item, as the total amount remains the same.
LEGAL NOTE
The Board is authorized to act on this matter pursuant to Chapter 125, Florida Statutes.
recommendation
RECOMMENDATION
It is recommended that the Board approve and authorize the Chairman’s signature on the attached Amendment No. 1 to Agreement No. WG026 with FDEP.