File #: 12327   
Type: Agenda Item Status: Adopted
File created: 5/23/2023 In control: Board of County Commissioners
On agenda: 6/13/2023 Final action: 6/13/2023
Enactment date: Enactment #:
Title: Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Frontage Road Addition at SR 50 and I-75 (Contract No. 19-C00102/DK; Amount: $25,646.66)
Attachments: 1. Final Pay Application #15 PO No. 19-C00102, 2. 19-C00102 Contract
TITLE
title
Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Frontage Road Addition at SR 50 and I-75 (Contract No. 19-C00102/DK; Amount: $25,646.66)

body
BRIEF OVERVIEW
The Frontage Road addition at SR 50 and I-75 paving project was awarded by the Board on July 16, 2019, Doc Id. No. 15935, to Goodwin Bros. Construction, Inc., in the amount of $2,064,687.76.

* Change Order One (1): No-cost time extension for additional work extending the project approximately thirty-five feet on each side of SR 50 to tie the roads into the Florida Department of Transportation (FDOT) widening of SR 50, adding 25 days; new completion date of August 29, 2020.

* Change Order Two (2): No-cost time extension to add 30 days due to a redesign within the work of Sherman Hills and for weather delays; new completion date of September 28, 2020.

* Change Order Three (3): Temporary Maintenance of Traffic (MOT) needed to provide access through the existing roadway into Sherman Hills. The FDOT SR 50 widening project is behind schedule holding up the Sherman Hills access roadway, increasing the contract by $8,512.50 from $2,064,687.76, to $2,073,200.26.

* Change Order Four (4): No-cost time extension to add 45 days; 35 days due to required additional work on Sherman Hills Boulevard alignment and 10 days for weather delay; new completion date of November 12, 2020.

* Change Order Five (5): An internal accounting change only to increase Line 1 to $120,509.49 and decrease Line 4 to $120,509.49, a no-cost change.

* Change Order Six (6): No-cost time extension for 88 days due to a conflict with FDOT project; new completion date of March 12, 2021.

* Change Order Seven (7): No-cost time 90-day extension due to a conflict with FDOT project; new completion date of June 10, 2021.

* Change Order Eight (8): No-cost time 90-day extension due to conflict with FDOT project; new completion date of September 8. 2021.

* Change Order Nine (9): No cost 90-day time extensio...