File #: 13078   
Type: Agenda Item Status: Adopted
File created: 10/24/2023 In control: Board of County Commissioners
On agenda: 11/28/2023 Final action: 11/28/2023
Enactment date: Enactment #:
Title: Reimbursement Agreement Between Hernando County Water and Sewer District and SIG Spring Hill Commercial, LLC, for County Line Road Force Main Extension Project
Attachments: 1. Reimbursement Agreement - Force Main Extension Project, 2. Approved Reimbursement Agreement Between Hernando County Water and Sewer District and SIG Spring Hill Commercial, LLC, for County Line Road Force Main Extension Project

TITLE

title

Reimbursement Agreement Between Hernando County Water and Sewer District and SIG Spring Hill Commercial, LLC, for County Line Road Force Main Extension Project

 

body

BRIEF OVERVIEW

SIG Spring Hill Commercial, LLC is developing a commercial subdivision along County Line Road west of Mariner Boulevard.  Hernando County Utilities Department (HCUD) has sewer infrastructure in the vicinity capable of providing sewer service to this project. 

 

As part of the agreement, HCUD has agreed to reimburse the Developer $298,827.00 for the construction costs incurred by the Developer to oversize the project’s sewer force main to a 12-inch which is required by HCUD.  The force main will start at the force main in County Line Road and run north approximately 390 feet to the lift station that will service the commercial development.  HCUD will reimburse the Developer once work has been completed, inspected, tested and accepted by HCUD.

 

FINANCIAL IMPACT

No financial impact at this time.

 

LEGAL NOTE

The Board has the authority to act on this matter pursuant to Chapter 125, Florida Statutes.

 

recommendation

RECOMMENDATION

It is recommended that the Board approve and authorize the Chairman’s signature on  the attached Reimbursement Agreement for SIG Spring Hill Commercial, LLC force main extension project.