Title: Final Close-Out of Contract With Deeb Construction & Development Co., for Weeki Wachee Woodlands Water Main Interconnect Project for Utilities Department (Contract No. 23-T00040-Q15; Amount: $136,763.31)
Attachments: 1. BOCC Approval 11-19-2024, 2. Contract 23-T00040AP - Deeb Construction and Development Co., 3. Amendment No. 1 to Contract No. 23-T00040 Q15, 4. Purchase Change Order No.1 25000494, 5. Purchase Change Order No. 2 25000494, 6. Final Pay Packet, 7. Expenditure Status Report 4121
TITLE
title
Final Close-Out of Contract With Deeb Construction & Development Co., for Weeki Wachee Woodlands Water Main Interconnect Project for Utilities Department (Contract No. 23-T00040-Q15; Amount: $136,763.31)

body
BRIEF OVERVIEW
Final Close-Out of Contract with Deeb Construction & Development Co. for Weeki Wachee Woodlands WM Interconnect project awarded by the Board on November 19, 2024, Doc Id. No. 14420, to Deeb Construction & Development Co. in the amount of $156,684.30.

Change Order One (1) decreased the contract $21,530.87 due to no gopher tortoises located in project area and increased it by $1,609.88 for updating plans to match what was found in the field was approved by the Chief Procurement Officer (CPO) on April 2, 2025, for an aggregate change of -$19,920.99. The Purchase order was decreased from $156,684.30 to $136,763.31.

Change Order Two (2) was CPO approved on April 3, 2025, for an administrative change to correct an error when entering Change Order #1. The Purchase Order amount was not affected and remained $136,763.31.

The Final Contract amount is $136,763.31 (PO No. 25000494).

The work has been completed and Deeb Construction & Development Co. has submitted its Final Pay Application No. One (1) in the amount of $136,763.31.

FINANCIAL IMPACT
Funding in the amount of $136,763.31 is available in the following account:

Fund: 4121 - HCUD Renewal and Replcmnt, Department: 07201 - Renewal and Replacement, Account: 5626302 - Improv-water line upgrade, No Retainage for this project.

LEGAL NOTE
The Board has the authority to act on this item pursuant to Part II, Chapter 2, Article V of the Hernando County Code of Ordinances. No notices of lien or claims of lien have been filed on the project.

recommendation
RECOMMENDATION
It is recommended the Board approve final pay Request No. One (1) in the amount of $136,763.31 to Deeb Construction & Development Co., to close out the Weeki Wachee Woodlands Water Main Interconnect project ...