Title: Final Close-Out of Contract With U.S. Water Services Corporation for Hill 'N Dale Water Main Replacement Project (Contract No. 21-C00027/DK; Amount: $139,498.78)
Attachments: 1. 21-C00027 - Contract, 2. Change Order #1, 3. Change Order #2, 4. Change Order #3, 5. FInal Pay #4 Packet
TITLE
title
Final Close-Out of Contract With U.S. Water Services Corporation for Hill 'N Dale Water Main Replacement Project (Contract No. 21-C00027/DK; Amount: $139,498.78)

body
BRIEF OVERVIEW
Final Close-Out of Contract with US Water Services Corporation for Hill 'N Dale Water Main Project awarded by the Board on June 8, 2021, Doc Id. No. 18337, to US Water Services Corporation in the amount of $777,940.00.

Change Order One (1) was requested for a no-cost time extension to add 93 days to the substantial completion date for a new date of January 9, 2023, and to add 153 days to the final completion date with a new date of May 9, 2023. The purchase order amount remains $777,940.00.

Change Order Two (2) was requested for a no-cost time extension to add 214 days to the substantial completion date for a new date of August 11, 2023, and to add 143 days to the final completion date with a new date of September 29, 2023. The purchase order amount remains $777,940.00.

Change Order Three (3) requested for a no-cost time extension to add 59 days to the substantial completion date for a new date of October 9, 2023, and to add 93 days to the final completion date with a new date of December 31, 2023. The purchase order amount remains $777,940.00.

Change Order Four (4) will be completed after Board approval to increase purchase order by $4,653.20 due to numerous conflicts throughout that required field changes from the original plan and additional drilling was required. This project has been completed. The total increase is $4,653.20. Purchase order will be increased from $777,940.00 to $782,593.20.

The Final Contract amount is $782,593.20 (PO No. 21000922).

The work has been completed and US Water Services Corporation has submitted its Final Pay Application No. Four (4) in the amount of $139,498.78.

All releases properly include Hernando County. US Water Services Corporation has signed a release of lien.

FINANCIAL IMPACT
Funding in the amount of $139,498.7...