Legislation Details

File #: 17927   
Type: Agenda Item Status: Agenda Ready
File created: 8/28/2026 In control: Board of County Commissioners
On agenda: 9/22/2026 Final action:
Enactment date: Enactment #:
Title: Change Order No. 5 to Purchase Order With Hydro-Klean, LLC, for Hernando Beach Wastewater Resiliency Manhole Coating Project for Utilities Department (Contract No. 24-TFG00704; Amount: $18,750.00)
Attachments: 1. BOCC Approval No. 14279, 2. Contract No. 24-TFG00704 - Solicitation Offer, 3. BOCC Approval No. 15722, 4. Contract No. 24-TFG00704 - Notice of Award, 5. Contract No. 24-TFG00704 Q5 - Executed Work Authorization Agreement, 6. Contract No. 24-TFG00704 Q5 - Notice of Award, 7. Purchase Order No. 25000763, 8. Change Order No. 1, 9. Change Order No. 2 & BOCC approval, 10. Change Order No. 3, 11. Change Order No. 4, 12. Change Order No. 5, 13. 411 exp, 14. 412 exp
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TITLE
title
Change Order No. 5 to Purchase Order With Hydro-Klean, LLC, for Hernando Beach Wastewater Resiliency Manhole Coating Project for Utilities Department (Contract No. 24-TFG00704; Amount: $18,750.00)

body
BRIEF OVERVIEW
On July 30, 2024, the Board approved Contract No. 24-TFG00704/AP Construction Services Under $500K for Grant Projects (Agenda Item No. 14279), pre-qualifying firms under four categories, A-Public Works, B-Waterways, C-Utilities, and D-Facilities, to provide quotes for County projects as needed.

On May 13, 2025, the BOCC approved award of Contract No. 24-TFG00704 Quote No. 5 to Hydro-Klean LLC for the Hernando Beach Wastewater Resiliency Manhole Coating project for $295,086.00.

The purchase order No. 25000763 was originally issued for $295,086.00. Change Order No. 5 in the amount of $18,750.00 would increase the purchase order to $514,154.50.

Change Order No. 1 was approved by the Chief Procurement Officer (CPO) on October 22, 2025, for a no-cost time extension.

Change Order No. 2 in the amount of $200,318.50 was approved by the Board on November 18, 2025, to add 44 manholes including ring/cover replacements, inflow protectors, grouting, and coating manhole; add one pump station to include grouting and coating.

Change Order No. 3 was a no cost change order to extend the final completion date, this was CPO approved on January 30, 2026, for ample time to complete work on project.

Change Order No. 4 was a no cost change order to extend the final completion date, this was CPO approved on April 14, 2026, for ample time to complete items on Final punch list.

Hernando County Utilities Department is requesting Change order No. 5 due to unknown field conditions where the contractor discovered more brick chimneys in the manholes than previously known. This change order will be for chimney removal and concrete riser installation.

STRATEGIC PLAN INITIATIVES
NA

FINANCIAL IMPACT
Funding in the amount of $18,750.00 is available in the fo...