Title: Amendment No. 3 to Contract With Friends Recycling, LLC, for Hernando County Recyclable Processing (Contract No. 21-T00030/DK)
Attachments: 1. Contract 21-T00030 With Friends Recycling, LLC 06.22.2021, 2. BOCC Approval of Award 06.22.2021, 3. Amendment No. One to Contract No. T21-T00030/DK - Recyclable Processing, 4. Amendment No. Two to Contract No. 21-T00030/DK for Recyclable Processing, 5. Amendment No. Three to Contract No. 21-T00030/DK for Recyclable Processing, 6. Letter - Friends Recycling, LLC Processing Fee Increase, 7. Expenditure Status Report 4411 07603 as of 4 25 24, 8. Public Comment Form - Jerry Lourenco, 9. Approved Amendment No. 3 to Contract With Friends Recycling, LLC, for Hernando County Recyclable Processing

TITLE

title

Amendment No. 3 to Contract With Friends Recycling, LLC, for Hernando County Recyclable Processing (Contract No. 21-T00030/DK)

 

body

BRIEF OVERVIEW

On June 22, 2021, Hernando County awarded a contract to Friends Recycling, LLC under Contract No. 21-T00030/DK to provide Recyclable Processing.

 

Amendment No. One was processed on August 23, 2022, to increase the price per ton from $45.00 to $49.10.  Amendment No. Two was processed on September 14, 2023, to increase the price per ton from $49.10 to $50.57.

 

The Hernando County Landfill Department is requesting Amendment No. 3 for a price increase from $50.57 to $95.57 per ton as requested by Friends Recycling, LLC.

 

Friends Recycling, LLC is requesting a price increase in the amount of $45.00 per ton due to the rising costs to Friends Recycling, LLC for fees associated with processing Hernando County material.  This increase will bring the price from $50.57 to $95.57 per ton.  Prior annual estimate of $217,451.00 will be increased by $193,500.00 with a new annual estimate of $410,951.00.

 

The Chief Procurement Officer has reviewed this requirement for conformance to Procurement Ordinance and Purchasing Policies and Procedures.

 

FINANCIAL IMPACT

Funding is available in Fund:  4411 - Solid Waste and Recycling, Department:  07603 - Recycling Operations, Account:  5303401 - Contracted Services.  New estimated annual amount of $410,951.00.

 

LEGAL NOTE

The Board has the authority to act on this item pursuant to Chapter 125, Florida Statutes.

 

recommendation

RECOMMENDATION

It is recommended the Board approve Amendment No. Three to Contract No. 21-T00030/DK for Hernando County Recyclable Processing.