TITLE
title
Discussion Regarding Proposed Median Improvement to Mariner Boulevard from Landover Boulevard to Elgin Boulevard
body
BRIEF OVERVIEW
Overview and discussion of proposed improvement to the median on Mariner Boulevard from Landover Boulevard northerly to Elgin Boulevard. The improvements include creating right in/right out driveway connections, left turn lanes at designated intersections, and a right turn lane at the Elgin/Mariner intersection. The project was divided into three (3) areas and crash data reviewed for each section from January 1, 2020, to January 1, 2025.
1) Landover Boulevard to Augustine Road
a. Total Crashes 403
b. 3 Fatal, 23 Incapacitating, 43 Non-Incapacitating, 59 Injury, 275 No Injury
2) Noremac Street to Mayberry Road
a. Total Crashes 26
b. 0 Fatal, 2 Incapacitating, 1 Non-Incapacitating, 3 Injury, 20 No Injury
3) Elgin/Mariner Intersection
a. Total Crashes 138
b. 1 Fatal, 2 Incapacitating, 12 Non-In-Capacitating, 11 Injury, 112 No Injury
FINANCIAL IMPACT
Estimated Cost for all improvements is $2,500,000. Inclusion of the improvements into the Capital Improvement Plan (CIP) will determine when the financial impact occurs, and the funding mechanism approval will take place with future CIP budget approvals.
The current CIP 112060 Mariner Boulevard Medium Improvements includes a FY27 Budget of $700,000 for Construction. Upon approval from the Board to update all improvements, the Current CIP project will be updated to the estimated cost of $2,500,000.
LEGAL NOTE
The Board has the authority to act on this matter pursuant to Chapter 125, Florida Statutes.
recommendation
RECOMMENDATION
It is recommended that the Board approve to make the median modification improvements between Landover Boulevard and Augustine Road and improve the Elgin Boulevard/Mariner Boulevard Intersection.