Hernando County, FL Banner Image
File #: 10780   
Type: Agenda Item Status: Adopted
File created: 7/12/2022 In control: Board of County Commissioners
On agenda: 8/9/2022 Final action: 8/9/2022
Enactment date: Enactment #:
Title: Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Anderson Snow Road Force Main Project (Contract No. 19-R00007-50; Amount: $10,312.78)
Attachments: 1. PayApp#2

TITLE

title

Final Close-Out of Contract With Goodwin Bros. Construction, Inc., for Anderson Snow Road Force Main Project (Contract No. 19-R00007-50; Amount: $10,312.78)

 

body

BRIEF OVERVIEW

The Anderson Snow Road Force Main was awarded by the Board on October 26, 2021, under Qualifications Contract No. 19-R00007 with assigned Quote No. Fifty (50) to Goodwin Bros. Construction Inc. in the amount of $135,444.97.

 

Change Order No. One (1) is a decrease to actual materials used, decreasing the Contract amount by $19,799.56 from $135,444.97, to $115,645.41.

 

The final Contract amount is $115,645.41 (PO No. 22000315).

 

The work has been completed and Goodwin Bros. Construction Inc. has submitted its Final Pay Application No. Two (2) in the amount of $10,312.78.

 

FINANCIAL IMPACT

Funding in the amount of $10,312.78 is available in the following account: Expense Account 4121-07201-5626322 Renewal and Replacement, Improv-Sewer Line Upgrade in the amount of $4,768.96 and

Retainage Account 4121-2050067 in the amount of $5,543.82.

 

LEGAL NOTE

Legal Authority under F.S. Chapter 125 (All releases properly include Hernando County).

 

recommendation

RECOMMENDATION

It is recommended the Board approve final pay request No. Two (2) in the amount of $10,312.78 to Goodwin Bros. Construction Inc. to close out Contract No.19-R00007 Qualifications Contract, Quote No. Fifty (50) for the Anderson Snow Road Force Main.

 

The final Contract amount is $115,645.41, a Contract amount decrease of $19,799.56 over BOCC award.