Title: Award of Sole Source Contract to DEEB Construction and Development Company for Water Main Interconnect From Verano Subdivision to Valley Falls Loop in Wellington Subdivision (Amount: $71,503.91)
Attachments: 1. Memorandum - Verano to Wellington Subdivision 8-Inch Water Main Interconnect, 2. Request for Quote, 3. Deeb Construction and Development Co., Sole/Source Justification, 4. Budget Amendment - Verano Sub-Wellington-Sub Water Main

TITLE

title

Award of Sole Source Contract to DEEB Construction and Development Company for Water Main Interconnect From Verano Subdivision to Valley Falls Loop in Wellington Subdivision (Amount: $71,503.91)

 

body

BRIEF OVERVIEW

The Hernando County Utilities Department is requesting Single Source award to Deeb Construction and Development for installation of a new 8-inch water main interconnect for the Wellington Subdivision. This interconnect is identified in the 2021 Water Master Plan.  Deeb Construction and Development has been contracted by the developer for the Verano subdivision, to be constructed between Wellington and County Line Road.

 

Single Source approval and award to Deeb Construction and Development will result in efficiency and cost savings for Hernando County due to Deeb Construction and Development being able to complete the interconnection at the time of construction of the subdivision.

 

Hernando County Utilities Department has received a quote in the amount of $71,503.91 from Deeb Construction and Development for this project.

 

The Chief Procurement Officer has reviewed this requirement for conformance to the Procurement Ordinance and Purchasing Policies and Procedures.

 

FINANCIAL IMPACT

Funding to award the Contract in the amount of $71,503.91 is available in Expense Account No. 07213-5626302 Connection Fees-Water, Improv-Water Line Upgrade.

 

LEGAL NOTE

In accordance with Part II, Chapter 2, Article V of the Hernando County Code of Ordinances.

 

recommendation

RECOMMENDATION

It is recommended that the Board approve award of Single Source Contractor Deeb Construction and Development for Verano Subdivision to Wellington Subdivision 8-inch water main interconnect in the amount of $71,503.91 and authorize the Chief Procurement Officer to approve change orders as they become necessary and required.